20 labour take 15 days to complete a work. how many labour must be added to complete the same work in 12 days

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:00
You got a job selling magazines door-to-door. you are paid $100 per day plus $1.50 for each magazine you sell. which recursive formula models this situation?
Answers: 1
question
Mathematics, 21.06.2019 20:40
Michelle is planting flowers in her garden. she wants the ratio of daises to carnations to be 3 to 2. michelle wants to plant a total of 35 flowers. how many daises should she plant?
Answers: 3
question
Mathematics, 21.06.2019 22:30
The moats separating people from the animals are 5 m wide for lions and 4 m wide for the elephants. if the lion’s moat is 4 m deep, how deep should the elephants’ moat be?
Answers: 1
question
Mathematics, 22.06.2019 01:00
Multiply: 2.7 × (–3) × (–1.2). a. –9.72 b. –10.8 c. 10.8 d. 9.72
Answers: 2
You know the right answer?
20 labour take 15 days to complete a work. how many labour must be added to complete the same work i...
Questions
question
History, 08.09.2019 04:10
question
Chemistry, 08.09.2019 04:10
Questions on the website: 13722362