A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. 1) Draw the project network. Complete the project schedule
2) can they complete the project in 30 days?
3) Critical path is?
4) Which activity has the most slack?
Solve without using computer
Activity Time Immediate Predecessor
A. Find client 4
B. Write prospectus 2 A
C. Obtain approval from client and professor 3 B
D. Complete programming 12 C
E. Do industry background research 10
F. Write final paper 6 D, E
G. Write oral report 5 D, E

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
Last month, a 770 g box of cereal was sold at a grocery store for $3.10. however, this month, the cereal manufacturer launched the same cereal in a 640 g box, which is being sold at $2.50. what is the percent change in the unit price?
Answers: 1
question
Mathematics, 21.06.2019 23:00
The table below shows the function f. determine the value of f(3) that will lead to an average rate of change of 19 over the interval [3, 5]. a. 32 b. -32 c. 25 d. -25
Answers: 2
question
Mathematics, 21.06.2019 23:00
Someone answer this asap for gabriella uses the current exchange rate to write the function, h(x), where x is the number of u.s. dollars and h(x) is the number of euros, the european union currency. she checks the rate and finds that h(100) = 7.5. which statement best describes what h(100) = 75 signifies? a. gabriella averages 7.5 u.s. dollars for every 100 euros. b. gabriella averages 100 u.s. dollars for every 25 euros. c. gabriella can exchange 75 u.s. dollars for 100 euros. d. gabriella can exchange 100 u.s. dollars for 75 euros.
Answers: 1
question
Mathematics, 22.06.2019 00:00
What is the measure of each of the two angles formed by the bisector of the diagonal of a rhombus if the original angle measures 58 degrees?
Answers: 1
You know the right answer?
A senior MIS design class project team has developed the following schedule of activities for their...
Questions
question
Mathematics, 18.11.2020 17:50
question
Chemistry, 18.11.2020 17:50
question
Mathematics, 18.11.2020 17:50
question
Computers and Technology, 18.11.2020 17:50
question
Physics, 18.11.2020 17:50
question
English, 18.11.2020 17:50
Questions on the website: 13722361