One worker does a job in 12 days, another does the same job in 15 days and a third in 20 days. What part of the job will be comleted if all three work together for four days?​

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 22:00
Describe how you can act financially responsible.
Answers: 1
question
Mathematics, 22.06.2019 01:30
What is the t intercept of the line given by the equation below y= -10x + 14
Answers: 3
question
Mathematics, 22.06.2019 02:30
An ice cream shop sells 5 times as many cakes cones as waffle cones. use x to represent the number of waflle cones the ice cream shop sells and use the variable to write an expresion for the number of cake cones the ice cream shop sells. enter the expression for the number of cake cones the the ice cream shop sells
Answers: 3
question
Mathematics, 22.06.2019 03:00
Which rotation about its center will carry a regular hexagon onto itself
Answers: 3
You know the right answer?
One worker does a job in 12 days, another does the same job in 15 days and a third in 20 days. What...
Questions
Questions on the website: 13722363