subject
Mathematics, 16.04.2021 17:40 andr8aa

A contractor employed 60 men to do a certain job in 15 days. How
many laborers working at the same
rate could complete the work in 4
days?​

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Geometry: determine whether segment mn is parallel to segment kl. justify your answer. jm 6 mk 3 jn 8 nl 4
Answers: 3
question
Mathematics, 21.06.2019 18:30
The formula for the lateral area of a right cone is la = rs, where r is the radius of the base and s is the slant height of the cone.which are equivalent equations?
Answers: 3
question
Mathematics, 21.06.2019 21:30
Aye asap pls ! markin da brainiest too ! btw da step choices are all add, distribute, divide, n subtract
Answers: 2
question
Mathematics, 21.06.2019 22:30
Which of the following graphs could represent a quartic function?
Answers: 1
You know the right answer?
A contractor employed 60 men to do a certain job in 15 days. How
many laborers working at the...
Questions
question
Mathematics, 23.04.2020 12:29
question
Mathematics, 23.04.2020 12:29
question
Mathematics, 23.04.2020 12:29
question
Mathematics, 23.04.2020 12:29
question
Mathematics, 23.04.2020 12:29
question
Mathematics, 23.04.2020 12:29
Questions on the website: 13722361