10 workers can paint a building in 21 days. If work has to be finished in 15 days, how many extra workers are required?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 22:30
Julie was able to walk 16 km through the zoo in 6 hours. how long will it take her to walk 24 km through the zoo?
Answers: 2
question
Mathematics, 22.06.2019 02:30
What is the slope-intercept form of a line that passes through points (2, 11) and (4, 17)? y=-3x-5 o y=3x-5 y=-3x+5 0y=3x+5
Answers: 2
question
Mathematics, 22.06.2019 04:00
Real gross domestic product: a) will increase if the price level increases. b) can change from one year to the next even if there is no change in output. c) will increase if the level of output increases. d) is a measure of inflation.
Answers: 3
question
Mathematics, 22.06.2019 04:20
The range of the following relation r {(3, -5), (1, 2), (-1, -4), (-1, 2)} is (1 point){-4, -5, 2, 2){-1, 1, 3){-1,-1,1,3){-5, -4,2)
Answers: 1
You know the right answer?
10 workers can paint a building in 21 days. If work has to be finished in 15 days, how many extra wo...
Questions
question
Geography, 17.10.2020 18:01
question
Mathematics, 17.10.2020 18:01
question
Mathematics, 17.10.2020 18:01
question
History, 17.10.2020 18:01
question
Physics, 17.10.2020 18:01
question
Mathematics, 17.10.2020 18:01
question
Mathematics, 17.10.2020 18:01
question
Mathematics, 17.10.2020 18:01
Questions on the website: 13722359