A project consists of replacing the track on an existing railroad line, involving 3,000 feet of track. The old track can be removed at a rate of 70 feet per hour. The old railroad ties can be removed at a rate of 200 feet (measured along the track) per hour. The new ties can be installed at a rate of 25 feet per hour, and the replacement track can be installed at a rate of 40 feet per hour. Show this operation on a linear schedule. Assume that the minimum float (buffer) for an activity at any location is 1 day.

ansver
Answers: 3

Another question on Physics

question
Physics, 21.06.2019 20:00
Player kicks a soccer ball from ground level and sends it flying at an angle of 30 degrees at a speed of 26 m/s. what is the horizontal velocity component of the ball to the nearest tenth of a m/s?
Answers: 2
question
Physics, 21.06.2019 21:20
The a metal retainer that keeps the rolling elements evenly spaced. n a. seal n b. separator n c. bearing n d outer race
Answers: 1
question
Physics, 22.06.2019 06:50
Much of the information taught in earth-space science would not be available if it weren’t for our remote sensing abilities. explain two ways our remote sensing strategies contribute to our knowledge of these topics.
Answers: 3
question
Physics, 22.06.2019 16:00
A( developed during the process of technology design
Answers: 3
You know the right answer?
A project consists of replacing the track on an existing railroad line, involving 3,000 feet of trac...