Meghan's team is comprised of 10 people who work 40 hours per week. The team is tasked with completing a project that requires 700 man-hours
in one week. To complete the project, Meghan plans to add n members to
the team and have each team member work an extra 3n hours that week.
What is the minimum number of extra team members she needs?

ansver
Answers: 3

Another question on SAT

question
SAT, 25.06.2019 04:30
The authors use the word β€œbackbone” in lines 3 and 39 to indicate that
Answers: 1
question
SAT, 25.06.2019 06:00
You are getting ready to transport troops in a m1152 configured with cargo cover and troop seats which of the following should you do before starting out
Answers: 1
question
SAT, 26.06.2019 09:30
What is the highest grade you can score on the act
Answers: 2
question
SAT, 26.06.2019 13:30
Auser wants to add a thick, dark green border around a chart in powerpoint. the user can do this in chart tools by choosing what
Answers: 1
You know the right answer?
Meghan's team is comprised of 10 people who work 40 hours per week. The team is tasked with complet...
Questions
question
History, 21.06.2019 17:00
Questions on the website: 13722360