Business, 19.10.2021 16:50 savagesquid4807

A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish time is 35 weeks, and the project variance is 7 weeks. If the project deadline is set to be 36 weeks, then what is the probability that the project would need more than the given deadline to complete

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 09:30
Cash flows during the first year of operations for the harman-kardon consulting company were as follows: cash collected from customers, $385,000; cash paid for rent, $49,000; cash paid to employees for services rendered during the year, $129,000; cash paid for utilities, $59,000. in addition, you determine that customers owed the company $69,000 at the end of the year and no bad debts were anticipated. also, the company owed the gas and electric company $2,900 at year-end, and the rent payment was for a two-year period.
Answers: 1
question
Business, 22.06.2019 15:20
Capital financial corporation will lend 90 percent against account balances that have averaged 30 days or less; 80 percent for account balances between 31 and 40 days; and 70 percent for account balances between 41 and 45 days. customers that take over 45 days to pay their bills are not considered acceptable accounts for a loan. the current prime rate is 16.50 percent, and capital charges 3.50 percent over prime to charming as its annual loan rate. a. determine the maximum loan for which charming paper company could qualify.
Answers: 1
question
Business, 22.06.2019 19:10
Imagine us is a startup that offers high definition 3d prenatal ultrasounds for high-end customers. the service process includes four activities that are conducted in the sequence described below. (the time required for each activity is shown in parentheses): activity 1: welcome a patient and explain the procedure. (20 minutes)activity 2: prep the patient (e.g., show them to the room, apply ultrasound gel). (17 minutes) (*your id number represents the amount of time needed to complete this task)activity 3: take images. (5 minutes)activity 4: discuss diagnostic with patient. (20 minutes)at each location there are employees (servers) s1, s2, and s3. the assignment of tasks to servers is the following: s1 does activities 1 and 2.s2 does activity 3.s3 does activity 4.a. what is the capacity of this process (in customers per hour)? b. suppose 3 patients arrive every hour on average. ignoring any “start of day” or “end of day” effects, what are the utilizations of all three servers (%)? c. suppose each activity can be done by any server and any server can do any set of activities. however, each activity is done by only one server. for example, a possible assignment includes: s1 does activity 1, s2 does activity 2, and s3 does activities 3 and 4. of course, the original assignment of servers to activities is also feasible. what is the maximum capacity of the process (in customers per hour)? d. now consider the capacity measures in (c) and (a), what is the percentage change? why can you improve capacity without using additional resources? (there is no free lunch, right? )note: for all hw assignments, show your process of getting the results. only providing the final answers is not acceptable and will get 0%. if necessary, use a separate sheet of paper to show your work.
Answers: 3
question
Business, 22.06.2019 20:00
Assume the perpetual inventory method is used. 1) the company purchased $12,500 of merchandise on account under terms 2/10, n/30. 2) the company returned $1,200 of merchandise to the supplier before payment was made. 3) the liability was paid within the discount period. 4) all of the merchandise purchased was sold for $18,800 cash. what effect will the return of merchandise to the supplier have on the accounting equation?
Answers: 2
You know the right answer?
A future project has an uncertain finish time and the finish time follows a normal distribution. The...
Questions
Questions on the website: 13722360