To complete a task in 30 days a company needs
4 people each working for 7 hours per day.
The...
Mathematics, 13.06.2021 18:30 KubraDskn
To complete a task in 30 days a company needs
4 people each working for 7 hours per day.
The company decides to have
5 people each working for 6 hours per day.
Assuming that each person works at the same rate,
how many days will the task take to complete?
Answers: 3
Mathematics, 21.06.2019 17:30
Using the side-splitter theorem, daniel wrote a proportion for the segment formed by luke segment de. what is ec?
Answers: 3
Mathematics, 21.06.2019 20:00
He weights of 2-pound bags of best dog food are approximately normally distributed with a given mean and standard deviation according to the empirical rule, what percentage of the bags will have weights within 3 standard deviations of the mean? 47.5%68%95%99.7%
Answers: 3
Social Studies, 29.07.2019 17:30
Health, 29.07.2019 17:30
Biology, 29.07.2019 17:30
Biology, 29.07.2019 17:30
History, 29.07.2019 17:30
Chemistry, 29.07.2019 17:30